In response to various queries that we receive from time to time, we have included below a few FAQs relating to the reservoir and dam works: When will we be able to walk across the dam? If it is safe to do so, we are hoping to temporarily open the footpath along the crest of […]

Read Full Post »

November 2011 update

Most of the main works to the north of the canal are now complete, although we still have to install drainage pipes through the sheet piles and carry out further landscaping works on the north eastern area next to pool cottages. The repair works to the canal basin are also nearing completion, although the reconstruction […]